Construction activities for the Connecting Link Project are scheduled to begin on Monday, August 8.

Miller Paving will start work next week on the Bruce Avenue intersection. For August 8 to August 12, work will include curb removal, culvert replacement and lighting pole removals, involving some lane closures. The outside lane on Highway 101, adjacent to the concrete island at Bruce Avenue, and the ramp to Bruce Avenue will be closed.

Excavation, ditching, culvert work and electrical work will continue on Highway 101 until August 26. Pulverizing of the existing pavement is scheduled to begin at the end of August with hot mix paving operations to follow shortly after.

The City of Timmins is committed to providing its residents with regular updates throughout this project, and more information will follow as work progresses.

Access to the cemetery and the Tisdale Transfer Site will be maintained.